I have visited many James Islanders over the last few weeks and I have often been asked about when the Folly/Camp and Harbor View Road projects are set to begin.
From Cal Oyer, the Construction Project Manager oof Charleston County Transportation Development:
"The current plan is to advertise Harbor View Rd in mid-June and receive bids late July. The best-case award date would be August 26, but we have to get SCDOT concurrence which could push award into mid to late September.
For Folly/Camp, we plan to re-advertise late July and receive bids late August. Best case award for Folly/Camp would be mid-September, but we have to get SCDOT concurrence which could push award into October."