Update on Folly and Camp and Harbor View Road Contracts


I have visited many James Islanders over the last few weeks and I have often been asked about when the Folly/Camp and Harbor View Road projects are set to begin.

From Cal Oyer, the Construction Project Manager oof Charleston County Transportation Development:


"The current plan is to advertise Harbor View Rd in mid-June and receive bids late July.  The best-case award date would be August 26,  but we have to get SCDOT concurrence which could push award into mid to late September. 

For Folly/Camp, we plan to re-advertise late July and receive bids late August.  Best case award for Folly/Camp would be mid-September, but  we have to get SCDOT concurrence which could push award into October."